Elijah Smith Building Chiller Replacement
Project Description
300 Main St, Whitehorse, YT Y1A 2B1
Project Cost: $1,800,000.00
The project includes the installation of two new 120-ton air-source chillers, a large heat exchanger, and associated pumps to modernize the building’s mechanical systems.
It involved the removal of existing water-source chillers and the cooling tower, along with comprehensive electrical and controls upgrades to enhance system efficiency and reliability. The scope also included a full rebuild of the boilers and the provision of temporary cooling and heating to maintain building operations throughout the project. The total project value was approximately $1.8 million.